Rate analysis for Concrete with Calculator – Step by Step

Rate analysis for Concrete Calculator

Rate analysis of PCC

Rate analysis of Brickwork

m³

How to Use Rate Analysis for Concrete Calculator?

Step 1: First of all, input the wet volume of PCC in cubic meters (m³) according to your requirements in Rate analysis for Concrete.

Step 2: After that, input the ratio of Cement, Sand, and Aggregate (for example, 1:1.5:3) according t  to design.

Step 3: Then, enter the number of masons and labors required per cubic meter in the fields based on your country. By default it will take value based on the IS code.

Step 4: Now, input the rates for all materials such as Cement, Sand, Aggregate, and labor in given table directly.

Step 5: Finally, click on “Calculate” button given at last of table to get the detailed rate analysis for concrete. This tool will helps you to calculate the total cost, sub-cost, overhead, and profit, along with the rate per cubic meter of PCC.

What is Rate analysis?

Rate analysis is the calculation of all costs of materials used for the construction of the concrete structure in the field of civil engineering.

Rate analysis is done before construction of the structure like a building, bridge, culvert, or road to get the approximate cost of full construction.

If we want to do the rate analysis for concrete then, we have to calculate the cost of all ingredients like cement, sand, aggregate, and steel used in the concrete. Besides this, we should also calculate the mason cost, mazdoor cost, labor cost, etc.

Purpose of rate analysis

The Purpose of rate analysis is to know the Unit cost of doing particular work or Project.
It is important to plan or to allocate the budget for the project. Hence rate analysis helps us to know the project cost and Budget to plan.

Data required to Rate analysis for Concrete

  • Materials like cement, sand, and aggregate
  • Steel
  • Workmanship like mason, labour
  • Shuttering charge
  • Water charge

Now let us take an example of question for Rate analysis for Concrete

Q) Calculate the rate analysis of 10 meter cube of concrete. The concrete mix is M15.

Rate analysis for Concrete with Calculator - Step by Step

Solution,

Step -1 Write all the known values of the materials

Here we should know that,

Total Concrete = 10 m3

M15 means the ratio of ingredient in concrete shoud be (Cement:Sand:Aggregate) = (1:2:4)

Density of cement = 1440 kg/m3

Density of steel reinforcement = 7850 kg/m3

Step -2 Calculate dry volume of concrete

For 10 Cubic meter concrete mix,

Total Dry volume = 10 + 52 % 0f 10 { We can take from 50% to 55% of additional volume of concrete to get dry volume}

= 15.2 cubic meter

Given, the mix ratio is 1:2:4

Let the quantity of cement be = x cubic meter

quantity of cement = 2x cubic meter

quantity of cement = 4x cubic meter

Step -3 Calculate volume of all materials

Then,

x + 2x + 4x = 15.2 cubic meter

7x = 15.2 cubic meter

x = 2.17  cubic meter

x = 2.2 15.2 cubic meter Approx.

Therefore Volume of cement = x = 2.2 cubic meter

Volume of Sand = 2x = 2 x 2.2 = 4.4 meter cube

Volume of Aggregate = 3x = 3 x 2.2 = 6.6 meter cube

Step -4 Convert volume of cement into numbers of bags

Now let us change the volume of cement into numbers of bags.

First of all change the volume of cement into weight i.e Kg.

So, weight = Volume x Density = 2.2 x 1440 = 3168 kg

Divide the total weight by 50 to get numbers of bags of cement.

So, numbers of bags of cement = 3168/50 = 63.64 bags = 64 bags Approx.

Step- 5 Calculate weight of steel rod

Now let us assume the 1% of steel has used in the concrete.

Then, 1 % of concrete volume becomes 0.1 meter cube of steel.

Therefore,

Weight of steel rod = volume x density = 0.1 x 7850 = 785 kg.

At last you can add water charges which is about 1.5% of total cost of the concrete.

and 10% contractors charges. If you are calculating for tenders.

Read Also, Easy way to calculate unit weight of steel rod

Table of Rate analysis for Concrete

Rate analysis for Concrete- Step by Step calculation with table
ParticularQuantityRateCost
Materails  Rs.
Aggregate
Sand
Cement
Steel
Binding wires
8.8 m3
4.4 m3
64 Bags
7.85 Quintal
1.5 Kg
2500 per m3
2400 per m3
350 per Bags
4400 per Q
65 per Kg
22000
10860
22400
34540
97.5
  Sub Total :-89597.5
Labour   
Mistri
Mason
Mazdoor  
½ no.
3 no.
12 no.
500 per day
400 per day
300 per day
250
1200
3600
  Sub Total:-5050
Binding, Cutting and Bending   
Blacksmith
Mazdoor
8 no.
8 no.
300 per day
250 per day
2400
2000
  Sub Total:-4400
Shuttering Timber and Planks  Lumsum1000 Rs.1000
Carpenters10 no.280 no.2800
  Total Amount:-Rs. 103,147.5

Q) Calculate the rate analysis of 15 meter cube of concrete. The concrete mix is M20.

Given,

  • Wet Volume of PCC (a): 5 m³
  • Cement: Sand: Aggregate ratio (b:c:d): 1:1.5:3
  • Mason required per m³ (mp): 0.5 Nos.
  • Labour required per m³ (lp): 3.5 Nos.
  • Rate of Cement (g): ₹750 per bag
  • Rate of Sand (e): ₹600 per m³
  • Rate of Aggregate (f): ₹1000 per m³
  • Rate of Water (l): ₹0.1 per liter
  • Manpower Rate (i, j): ₹1200 per mason and ₹500 per laborer
  • Overhead and Profit (k): 15%

The Rate of materials may varies according to you location and country.

Solution,

Step 1: Calculate Dry Volume of Concrete:

Dry Volume = Wet Volume × 1.54

Dry Volume = 5 × 1.54 = 7.7 m³

Step 2: Calculate Quantities of Materials for (M20 grade of concrete):

Here, Sum of ratio = (1:1.5:3) = 5.5

a. Cement Quantity = Dry Volume × (Cement ratio / Total ratio) = 7.7 × (1 / 5.5) = 1.4 m³

b. Sand Quantity = Dry Volume × (Sand ratio / Total ratio) = 7.7 × (1.5 / 5.5) = 2.1 m³

c. Aggregate Quantity = Dry Volume × (Aggregate ratio / Total ratio) = 7.7 × (3 / 5.5) = 4.2 m³

d. Water Quantity = 0.5 × Cement Quantity × 50 = 0.5 × 1.4 × 50 = 35 liters

Step 3: Calculate Costs of all materials

a. Cement Cost = Cement Quantity × Rate of Cement = 1.4 × ₹750 = ₹1050

b. Sand Cost = Sand Quantity × Rate of Sand = 2.1 × ₹600 = ₹1260

c. Aggregate Cost = Aggregate Quantity × Rate of Aggregate = 4.2 × ₹1000 = ₹4200

d. Water Cost = Water Quantity × Rate of Water = 35 × ₹0.1 = ₹3.5

Step 4: Calculate Labor Costs:

Mason Cost = Mason required × Rate per Mason × Number of Cubic Meters

= 0.5 × ₹1200 × 5 = ₹3000

Labor Cost = Labor required × Rate per Labor × Number of Cubic Meters

= 3.5 × ₹500 × 5 = ₹8750

Step 5: Calculate Total Cost:

Total Material Cost = ₹1050 + ₹1260 + ₹4200 + ₹3.5

= ₹6513.5

Total Labor Cost = ₹3000 + ₹8750 = ₹11750

Total Cost = ₹6513.5 + ₹11750 = ₹18263.5

Step 6: Add Overhead and Profit:

Overhead and Profit = 15% of ₹18263.5

= ₹2739.53

Final Total Cost = ₹18263.5 + ₹2739.53

= ₹20903.03

Step 7: Now, Calculate Rate per Cubic Meter of PCC:

Rate per Cubic Meter = ₹20903.03 / 5 = ₹4180.61

Hence in this way we can calculate the rate analysis for concrete, including material and labor costs, along with overhead and profit. I hope this article remains helpful for you.

Contributed by,

Civil Engineer – Ranjeet Sahani

Read Also,

Bar bending schedule for footing- Step by Step Procedure to Calculate

Dowel bars and Tie bars – Application and Installation and Advantages

Calculate weight of steel bar | Quantity of steel bar in circular slab

Share On:

"Structural Engineer" with over 5 years of proven expertise in estimation, structural design, and surveying. I specialize in creating safe, efficient, and sustainable structures that combine innovation with practicality.

Leave a Comment