Contractor Cost Estimator

Inputs:
A) Types of Civil Works
B) Input Quantity
C) Labor Costs
Estimated Cost/Labor
Total Labor Cost with Materials: Rs.0
Skilled Labor: 0, Unskilled Labor: 0
——————————————————————————————
Total Skilled Labor Cost: Rs.0
Total Unskilled Labor Cost: Rs.0
How to use Labour Cost Calculator for Construction Works?
Cost of labour for building construction works depends upon the rate of working skilled and unskilled labour per day. The number of skilled and unskilled labour required for different construction works are different and decided by the standard of different place and country.
In above calculator, I have used the standard rate of labour in Nepal. It may be different for different country.The number lo labour required will be approximately same for every counrty but the wages may be different and so the cost of labour for different civil construction works.
Here I have given step by step guide to use this calculator.
Step1:- First of all select the types of civil works.
Step2:- After that, input the qantity of works.
Step3:- Put the daily wages for the skilled and unskilled labour according to your country.
Step4:- Click on Calculate Button to get the result.
You will get the following result.
- Total cost of labour with materials.
- Weight of total steel Plate.Total number of skilled and unskilled labour.
- Total cost of skilled and unskilled labour.
How to calculate Cost of skilled and Unskilled Labour required for construction work?
Let we have a brick wall having length 50 meter, height 3 meter and of thickness 230 mm. The daily wages of unskilled labour is Rs.600 and Skilled labour is Rs.1200. Now, calculate the skilled and unskilled labour required for the brickwork for the wall.

Solution:-
Step1:- Calculate total volume of brickwork.
Volume = Length x width x height = 50 x 3 x 0.230
Volume = 34.5 meter cube
Step2:- Calculate the total skilled and unskilled labour required for brickwork acccording to the country code.
According to nepal, For 1 meter cube of brickwork we need 1.5 skilled labour and 2.4 unskilled labour.
Now, for 34.5 meter cube brickwork we will need,
Skilled labour = 34.5 x 1.5 = 51.57 Nos.
UnSkilled labour = 34.5 x 2.4 = 82.8 Nos.
Step3:– Calculate the total cost of labour
Cost of skilled labour = No. x Daily wages = 51.57 x 1200 = Rs. 61884
Cost of Unskilled labour = No. x Daily wages = 82.8 x 600 = Rs. 49680
Hence, In this way we can calculate the total cost of labour required for construction.
Read Also,
Volume of one bag cement Formula/Calculator – Site Working Numerical