Numerical Example – Cement Sand Aggregate Calculation for m20 Grade Concrete

Q. Calculate Quantity of Cement, Sand and Aggregate Required for 5 m³ of M20 Concrete.
Given,
Volume of Concrete = 5 m³
Grade of Concrete = M20
STEP-1 : Choose The Mix Ratio Of Concrete
Let take the mix proportion in M20 grade concrete as M20 (1:1.5:3).
It means that every 1 part of cement needs 1.5 parts of sand and 3 parts of aggregate.
STEP-2 Calculate The Total Dry Volume Of Concrete
Increase the concrete volume by 52 %.
Total Dry Volume = 5 x 1.52
= 7.6 m³
Note,
Dry Volume = Wet Volume * 1.54
STEP-3 : Cement Calculation
Cement quantity = (Cement Part)/(Sum of Mix) × Quantity of Concrete
Cement quantity = 1/5.5 × 7.6 = 1.382 m³
Sum of Mix = 1+1.5+3 = 5.5
Bags of cement = 1.382 × 1400/50 = 38.69 bags
Since,
Density of cement = 1440 kg
1 bag of cement = 50 kg
STEP-4 : Calculate Sand Quantity
Cement quantity = (Sand Part)/(Sum of Mix) × Quantity of Concrete
Quantity of Sand = 1.5/5.5 × 7.6
= 2.073 m³
STEP-5 : Calculate the Aggregate
Cement quantity = (Aggregate Part)/(Sum of Mix) × Quantity of Concrete
Quantity Aggregate quantity = 3/5.5 × 7.6
= 4.145 m³
Summary,
Required Cement = 38.69 bags
Required Sand = 2.073 m³
Required Aggregate= 4.145 m³