Cement Sand Aggregate Calculation for m20 Grade Concrete

Numerical Example – Cement Sand Aggregate Calculation for m20 Grade Concrete

Cement Sand Aggregate Calculation for m20 Grade Concrete

Q. Calculate Quantity of Cement, Sand and Aggregate Required for 5 m³ of M20 Concrete.

Given,

Volume of Concrete = 5 m³

Grade of Concrete = M20

STEP-1 : Choose The Mix Ratio Of Concrete

Let take the mix proportion in M20 grade concrete as M20 (1:1.5:3).

It means that every 1 part of cement needs 1.5 parts of sand and 3 parts of aggregate.

STEP-2 Calculate The Total Dry Volume Of Concrete

Increase the concrete volume by 52 %.

          Total Dry Volume = 5 x 1.52

                                         = 7.6 m³

Note,

     Dry Volume = Wet Volume * 1.54

STEP-3 : Cement Calculation

Cement quantity = (Cement Part)/(Sum of Mix)  × Quantity of Concrete

Cement quantity = 1/5.5  × 7.6 = 1.382 m³

Sum of Mix = 1+1.5+3 = 5.5

Bags of cement = 1.382 × 1400/50   = 38.69 bags

Since,

Density of cement = 1440 kg

1 bag of cement = 50 kg

STEP-4 : Calculate Sand Quantity

Cement quantity = (Sand Part)/(Sum of Mix)  × Quantity of Concrete

Quantity of Sand =  1.5/5.5 × 7.6

                            = 2.073 m³

STEP-5 : Calculate the Aggregate

Cement quantity = (Aggregate Part)/(Sum of Mix)  × Quantity of Concrete

Quantity Aggregate quantity = 3/5.5 × 7.6

                                              = 4.145 m³

Summary,

Required Cement = 38.69 bags

 Required Sand = 2.073 m³

 Required Aggregate= 4.145 m³

Download PPT

Watch Video on Cement Sand Aggregate Calculation for m20 Grade Concrete

Read Also,

Ready Mix concrete bags Calculator

How many bags of concrete Calculator

Concrete materials Calculator

Share On:

"Structural Engineer" with over 5 years of proven expertise in estimation, structural design, and surveying. I specialize in creating safe, efficient, and sustainable structures that combine innovation with practicality.